HydraGlyde System Improves ROP 60%, Drills 1.5¡Á Faster in Permian Basin Lateral Wells

Published: 03/23/2016

Concrete blue texture
HydraGlyde System Chart
Using the HydraGlyde system, the operator drilled the production interval in 4.38 days, 1.5¡Á faster than the average time spent drilling offset wells with OBM. The average ROP of the lateral sections (excluding the build section) drilled with the HydraGlyde system was 138.8 ft/h, a 60% increase compared with the average of seven offset wells drilled with OBM.
Location
Permian Basin, United States, North America, Onshore
Details

Wolfcamp Shale

Measured depth
15,580 ft [4,749 m]

True vertical depth
9,520 ft [2,902 m]

Production hole section
8 3/4 in × 8 1/2 in

Production casing
5 1/2 in

Lithology
Interbedded shale and limestone

Background
An operator used an oil-base mud (OBM) in previous wells drilled in the Midland basin¡¯s Wolfcamp Shale, but the resulting hauloff requirements increased overall well cost. The operator sought a solution to match or exceed the ROP achieved using the OBM without increasing hauloff or cuttings disposal costs.